What preparations should be made before using anchors

2023/07/17 10:17

Mining anchor is a very important construction material, but this product has strict requirements for the production materials. Here our manufacturer tells you about the production materials of mining anchor rods. I hope you can read it carefully. If you have different opinions, please feel free to call us for feedback. Meanwhile, we also suggest you collect this article for future reference when you need it, let's take a look at this article.

Mining anchor support can not be separated from resin anchors, anchors, steel straps, anchor trays, nuts and other materials, all have certain requirements. Material requirements for anchor support: steel belt or reinforcing beam: the tensile strength of the material should not be less than 360MPa.

Mining anchor manufacturers should provide qualified and stable products. The color of the hardener in the anchoring agent shall comply with the provisions of the industry standard. The performance, characteristics, external dimensions, mixing time, initial setting time and proper use of the anchoring agent shall be described in the product specification. Mixing of anchoring agents from different manufacturers within the mine with resin anchoring agents is not allowed.


Mining anchor


The warehouse manager in charge of bolt holders shall register the name, specification, quantity, production date, arrival time and distribution of each batch. The storage period shall not exceed the requirements of the product specification, and the temperature of the warehouse shall be 4-25℃. Anchor rods (including truss tie rods, etc.): metal rod body tensile yield strength of not less than 320MPa, tensile strength of not less than 500MPa, elongation rate of not less than 16.

Before hitting the front, first in accordance with the center, waist line strictly check the specifications of the section of the roadway, does not meet the requirements of the operating procedures must be dealt with first; before hitting the front to knock the gang to ask about the top, carefully check the top of the gang surrounding the rock situation, deal with the dangerous rock, to confirm that the installation before the start of the operation, the location of the anchor rod eye should be accurate, the eye error shall not be more than 100mm, the eye error shall not be greater than 15 °. The depth of the anchor eye should be matched with the length of the anchor, and the eye should be marked on the braze when drilling, and the eye should be drilled strictly according to the length of the anchor, with a depth of 2650mm, which is not fixed, and after the anchor eye is drilled, the slag and water inside the eye should be cleaned up. When drilling the eye, it shall be operated under the cover of temporary support. The order of drilling shall be carried out from outside to inside, first top and then help.

a. Determine the position of anchor holes according to the design requirements, and drill the holes with drilling rigs.

b. Blow out the rock dust in the hole with pressurized air.

c. The diameter of the drilling hole should be 6-12mm larger than the diameter of the anchor rod.

d. Send the anchoring agent into the bottom of the hole with the anchor rod, start the mixing device for mixing, and strictly control the mixing time according to the requirements of resin anchoring agent.

e.Tighten the nut after reaching the waiting time.


Mining anchor